What’s the setting process of aluminum formwork?

 

Antai aluminum formwork is an early removing system with the working period of 5 days, compared to 14~30 days cycle with the conventional method.

 

1: Structural line and level check


2: Installation of electrical, plumbing components and steel rebar. Installation of I/C and wall panels


7_副本


3: Installation of beam and SC panels


1153616643


4: Installation of staircase panels


QQ图片20181105162829


5: Installation of slab panels


682082662


6: Removing of slab panels


6_副本


7Installation of electrical, plumbing components and steel rebar